ALCOSAN Initiates Design/Management Plan for Wet Weather Plant Expansion

Jan 25, 2018

Pittsburgh, PA : Expansion of the Woods Run Treatment Plant is the site for a major project that will take 9 to 10 years for design and completion. As currently scheduled, Construction Management firms will submit qualifications to ALCOSAN on February 7 - firms will then be shortlisted and asked to submit proposals during the first week of April.

Design procurement is scheduled for early July, 2018, and construction is expected to begin in the second quarter of 2020 with completion by the end of 2027.