Enrollment Increase Demands Expansion for North Allegheny Schools

Nov 29, 2018

Wexford, Pa : The North Allegheny School District has projected cost estimates for expansions/renovations at Franklin and McKnight Elementary Schools. Franklin Elementary is budgeted at $30 to $33 million , and McKnight Elementary at $20 to 23 million .

Architects at VEBH of Mt. Lebanon are in design development and bidding is expected mid to late first quarter of 2019.

Massaro Corporation of O'Hara Township is the Construction Manager for both projects.

To track these project for future updates please refer to our Project ID #2018-15C6 for Franklin Elementary and Project ID #2018-04D8 for McKnight Elementary.

As the projects are released for bidding, plans and specs will be available on our website .