Contracts Awarded For New Canon-Mac Middle School Phase 2

Nov 01, 2020

Canonsburg PA (Washington County) : On November 5, the Canon-McMillan School District board awarded seven of the eight contracts for the Phase 2 construction of a new $58 million middle school.

The successful contractors with base bid and accepted alternates:

General Construction: Walter Mucci Construction $33,553,170

HVAC: Lugaila Mechanical $9,120,000

Plumbing: Shipley Brothers Construction $2,258,600

Electrical: A-1 Electric $4,868,000

Fire Protection: Interstate Fire Protection $517,300

Food Service Eqpt: 11,400 Inc. $657,000

Technology: Horizon Information Services $399,000

Traffic Signalization - A. Folino Construction $483,483

Fire Protection bids were rejected .

Contracts were awarded in February for Site Construction ( Mele & Mele & Sons , $6,559,000) and Site Plumbing ( Independent Enterprises, Inc.) , $167,650).

HHSDR Architects/Engineers of Sharon is the primary design firm for the project.